NARANGBA AGED CARE

project profile

Location: Narangba North Brisbane
Client: Croft Developments
Contract Value: $1,589,000
Construction Period: 6 months
Description of works: Installation of Thermal & Acoustic Insulation, Plasterboard, Fibre cement wall & ceiling linings
for a 140 Bed Facility.

outcomes

Problem / Solutions:

Installation of 40,000m2 of linings in 6 month program

Our Solution / Our Management:

Onsite supervision was at the highest level including the installation Team creating above average level of finish with minimal call back.

Client Benefit / Value Adding:

Croft Development construct & operate the facilities once commissioned, having the ability to produce high levels of finish in a 6 month program creates the ability for the facility to operational in a shortened period of time. Croft Development then have the ability to generate their Return on Investment. .